Remediation works were undertaken at East Bergholt Primary School following a fire, comprising the installation of a new roof covering, new rooflights, replacement of the PV array, and a full programme of internal refurbishment to reinstate the building.
Following the initial emergency call, our team was on site within 45 minutes to secure the building and make it weathertight, preventing further damage while refurbishment plans were developed. With the fire occurring during the summer holidays, the works were carefully programmed and delivered at pace to ensure the school was ready to reopen safely for the new academic term in September.
Client
Suffolk County Council (Concertus)
Completion Date
September 2025
Design Team
Concertus Design and Property Consultants
Value
£200K